Puri Y Construction Updates

We are transforming the donated building from the Puri Family into our newest YMCA facility. We are creating a YMCA for all complete with a fitness center, exercise studios, youth family area and child watch area. Check back often for updates as we move closer to our Spring 2017 opening.

March 21 Update

Carpeting and lighting are installed! We are six weeks out until our opening day on April 29. We can see the spaces start to come alive.


 

March 9 Update

It certainly is taking shape! The painting is complete - we love some of the bright colors to motivate your workouts. The lockers are in and floors will be going in soon.

February 24 Update

It is starting to look more like a YMCA as our colors are starting to go up on the walls!

February 17 Update

The crews continue to make progress. A lot of attention has been focused on the HVAC system and sprinklers. The walls are being finished and some painting is beginning. 





 

February 10 Update

The space is becoming more defined as crews finish up with insulation, hanging drywall and taping.



 

February 1 Update

We're ruffing in walls and ceilings, and getting our inspections done.